Project Detail
Project Main Menu

Project Overview
Project Name: ES: 13714-13716 Kerrydale Road / Watershed: Neabsco Creek
Project Type: Drainage Improvement Project
Project Description: (Dale City Sec. 8C, Lot 60/61, Project Code Number: 5571) A stream bank along the rear property lines has eroded and is causing damage to a property fence. Design and stabilize the eroded area to prevent further loss of property.
Project Manager: Khalid Quraishi     send an email
Alternate Manager: Mukesh Patel     
Agency Name: Department of Public Works - Environmental Services QPR?: Yes
Magisterial District: Neabsco
Original Budget: $60,000.00

Revised Budget:

$60,000.00
Original Start Date: 1/1/2002

Revised Start Date:

Original End Date: 5/31/2004

Revised End Date:

8/31/2004
Last Updated On: 11/15/2004 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. Stormwater Management/Drainage Fund

$60,000.00 ---
       
Total Amount: $60,000.00 $60,000.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
   
1. Right of Entry 1/1/2002 2/1/2002    
2. Survey 10/27/2003 11/21/2003    
3. Design 3/1/2002 1/5/2004 3/31/2002 2/13/2004    
4. Corps of Engineers 2/23/2004 4/30/2004    
5. Construction 5/2/2004 7/15/2004 5/31/2004 8/31/2004    


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue