Project Name: ES: 9903 King George Drive
Project Type: Drainage Improvement Project
Project Description: (West Gate Sec. 1B, Project Code Number: 5552) Homeowner is experiencing severe water ponding (due to blocked drainage) in his backyard. Need to design and construct a storm drainage system to minimize water pooling, sogginess and mosquito nuisance.
Project Manager: Khalid Quraishi     send an email
Alternate Manager: Mukesh Patel     
Agency Name: Department of Public Works - Environmental Services QPR?: Yes
Magisterial District: Gainesville
Original Budget: $22,000.00

Revised Budget:

$22,000.00
Original Start Date: 4/1/2001

Revised Start Date:

Original End Date: 3/31/2002

Revised End Date:

8/15/2003
Last Updated On: 5/2/2004 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. Stormwater Management Fund/Drainage Fund

$22,000.00 ---
       
Total Amount: $22,000.00 $22,000.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
   
1. Right of Entry 4/1/2001 8/1/2001    
2. Survey 12/1/2001 1/31/2002    
3. Design 2/1/2002 3/15/2002    
4. Construction 9/12/2002 10/1/2002    
5. Plat Preparationand recordation 7/1/2002 5/15/2003 8/15/2003    


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue
8/20/2003The project is complete. This is the final report.

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue