Project Detail
Project Main Menu

Project Overview
Project Name: TD: Devils Reach Road Sidewalk
Project Type: Revenue Sharing - Sidewalk Construction
Project Description: Provide curb, gutter and a sidewalk west of Occoquan Road (Route 253)
Project Manager: Thomas J. Blaser     send an email
Alternate Manager: Kafayat U. Rahmani     
Agency Name: Transportation Division of Public Works QPR?: Yes
Magisterial District: Occoquan
Original Budget: $555,140.00

Revised Budget:

$555,140.00
Original Start Date: 6/1/2002

Revised Start Date:

Original End Date: 12/31/2004

Revised End Date:

8/31/2005
Last Updated On: 4/17/2006 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. FY03 - State Supplemental

$13,584.00 --- 7/1/2004

2. FY03-04 State Supplemental Allocation

$15,717.00 --- 7/1/2004

3. FY03-04 County Supplemental Allocation

$15,717.00 --- 7/1/2004

4. FY04 - County Allocation

$71,429.00 --- 7/1/2003

5. FY04 - State Allocation

$71,429.00 --- 7/1/2003

6. FY03 County Supplemental

$13,584.00 --- 7/1/2003

7. FY02 County Supplemental

$14,286.00 --- 7/1/2002

8. FY03 - State Allocation

$71,429.00 --- 7/1/2002

9. FY03 - County Allocation

$71,429.00 --- 7/1/2002

10. FY02 State Supplemental

$14,286.00 --- 7/1/2002

11. Transferred from Old Bridge Road Trail Project - Res #02-267

$182,250.00 --- 4/2/2002
       
Total Amount: $555,140.00 $555,140.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
   
1. Right-of-way Research 6/1/2002 10/31/2002    
2. Engineering Survey 11/1/2002 2/14/2003 12/31/2002 4/18/2003    
3. Engineering Design 1/1/2003 10/1/2003 4/1/2003 12/10/2003    
4. VDOT Approval 8/1/2003 4/30/2004 8/31/2003 8/31/2004    
5. Right-of-way/Easements Acquisition 9/1/2003 9/1/2004 10/31/2003 2/28/2005    
6. Relocation of Utilities 11/1/2003 3/1/2005 12/31/2003 3/31/2005    
7. Construction 1/1/2004 5/1/2005 5/31/2004 8/31/2005    
8.    


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue