Project Detail
Project Main Menu

Project Overview
Project Name: ES: 12718 Purdham Drive / Watershed: Occoquan River
Project Type: Drainage Improvement Project
Project Description: Storm water runoff from the backyard of several properties is flooding a homeowners' basement and causing the ponding of water in two backyards. Design and install a storm drain system to alleviate the problem.
Project Manager: Khalid Quraishi     send an email
Alternate Manager: Mukesh Patel     
Agency Name: Department of Public Works - Environmental Services QPR?: Yes
Magisterial District: Occoquan
Original Budget: $13,000.00

Revised Budget:

---
Original Start Date: 9/1/2002

Revised Start Date:

Original End Date: 4/30/2003

Revised End Date:

12/31/2003
Last Updated On: 8/2/2004 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. Stormwater Management Fund/Drainage Fund

$13,000.00 ---
       
Total Amount: $13,000.00 $13,000.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
   
1. Right of Entry 9/1/2002 10/15/2002    
2. Survey 10/15/2002 12/30/2002    
3. Design 2/15/2003 1/15/2003 3/15/2003 5/31/2003    
4. Meeting with homeowners and their approval 1/15/2003 2/15/2003 6/30/2003    
5. VDOT Land Use Permit 4/1/2003 6/1/2003 5/15/2003 7/15/2003    
6. Stake-out and cut sheet 8/14/2003 8/26/2003    
7. Construction 4/1/2003 10/6/2003 4/15/2003 12/31/2003    


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue
12/31/2003Project completed. This is the Final Report

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue