Project Detail
Project Main Menu

Project Overview
Project Name: ES: 4808 Pearson Drive / Watershed: Neabsco Creek
Project Type: Drainage Improvement Project
Project Description: Storm runoff is causing a homeowners backyard and basement to flood. Need to design and construct a storm drain system to minimize the storm water runoff problem.
Project Manager: Khalid Quraishi     send an email
Alternate Manager: Mukesh Patel     
Agency Name: Department of Public Works - Environmental Services QPR?: Yes
Magisterial District: Neabsco
Original Budget: $9,000.00

Revised Budget:

$9,000.00
Original Start Date: 5/1/2002

Revised Start Date:

Original End Date: 12/30/2002

Revised End Date:

Last Updated On: 5/2/2004 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. Stormwater Management Fund/Drainage Fund

$9,000.00 ---
       
Total Amount: $9,000.00 $9,000.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
   
1. Right of Entry 5/1/2002 6/30/2002    
2. Survey 7/1/2002 8/15/2002    
3. Design 8/15/2002 9/30/2002    
4. Construction 11/15/2002 12/15/2002    


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue