Project Detail
Project Main Menu

Project Overview
Project Name: PM: Owens Backfill
Project Type: Renovation
Project Description: OPSC outgrew their space in the existing bldg. Upon relocating OPSC to the new expansion wing, redesign original Owens bldg. to house Admin. personnel and OIT Networking.
Project Manager: Said G. Said     send an email
Alternate Manager: Linda J. Winslow     
Agency Name: Public Works, Property Mgmt. QPR?: Yes
Magisterial District: Coles
Original Budget: $609,000.00

Revised Budget:

$609,000.00
Original Start Date: 8/1/2002

Revised Start Date:

Original End Date: 7/31/2003

Revised End Date:

6/30/2004
Last Updated On: 11/12/2004 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. CIP

$609,000.00 --- 7/15/2002
       
Total Amount: $609,000.00 $609,000.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
Assigned
Staff
 
1. Interview prospective tenants to determine space requirements. 9/30/2002 1/10/2003 LJW&P&P  
2. Determine requirements for EOC room. Peck and Peck to prepare drawings. 8/1/2002 6/1/2003 Peck& Peck  
3. Prepare Renovations drawings. 11/13/2002 3/14/2003 Peck & Peck  
4. Submit plans to Building Development (1st)Review 3/17/2003 3/28/2003 Bldg. Dev.  
5. Revised plans (by architect) 3/31/2003 4/4/2003 Peck Peck  
6. Plan review by Building Development (2nd) 4/7/2003 4/17/2003 Bldg. Dev.  
7. Review bid documents 3/31/2003 4/18/2003 Purchasing  
8. Advertise Invitation for Bid (IFB) 4/21/2003 5/9/2003 Purchasing  
9. Bid Opening 5/12/2003 5/12/2003 PWC  
10. Prepare Board Agenda 5/13/2003 6/2/2003 Prop.Mgmt.  
11. Prepare furniture order 6/1/2003 6/15/2003 8/25/2003 Prop.Mgmt.  
12. Award contract 6/17/2003 6/24/2003 6/17/2003 6/24/2003 PWC BOCS  
13. Preconstruction meeting 7/1/2003 7/1/2003 Prop.Mgmt.  
14. Construction 7/1/2003 7/15/2003 10/15/2003 11/21/2003 Contractor  
15. Walk through, punch list 11/4/2003 12/30/2003 11/17/2003 1/20/2004 PWC &Contrator  
16. Furniture installation 11/8/2003 12/15/2003 12/1/2003 1/26/2004 Contractor  
17. Move & Occupancy 12/12/2003 2/3/2004 12/23/2003 2/12/2004 Prop.Mgmt.  
18. Project closeout 12/2/2003 2/13/2004 12/2/2003 6/30/2004 Prop.Mgmt.  


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue
9/17/2004PROJECT IS COMPLETED . THIS IS THE LAST REPORT ON THE PROJECT

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue