Project Name: ES: Mellott Road / Watershed: Neabsco Creek
Project Type: Drainage Improvement Project
Project Description: (Cow Branch Stream Improvements, Project Code Number: 5500) Severe erosion is occurring along the stream bank of Cow Branch near Mellott Road. The project involves a design to restore the stream banks followed by a stream restoration project. Note: Revised End Date to be determined.)
Project Manager: Maden Mohan     send an email
Alternate Manager: Wade A. Hugh     
Agency Name: Department of Public Works - Environmental Services QPR?: Yes
Magisterial District: Woodbridge
Original Budget: $200,000.00

Revised Budget:

$0.00
Original Start Date: 8/1/1996

Revised Start Date:

Original End Date: 10/31/2002

Revised End Date:

5/10/2004
Last Updated On: 11/15/2004 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. Capital Improvement Program

$200,000.00 $0.00
       
Total Amount: $200,000.00 $0.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
   
1. Design (Design Completion Date to be determined) 8/1/1996    
2. Survey 11/1/1996 12/1/1997    
3. Right of Entry 7/1/2001 7/31/2001 9/1/2003    
4. Construction 10/1/2002 10/31/2002 5/10/2004    


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue