Project Name: ESD: Marumsco Creek Regional Storm Water Mgmt. Ponds / Watershed: Marumsco Creek
Project Type: Capital Improvement Project
Project Description: (Upstream of Interstate 95 on Marumsco Creek) Public Works will design two wet ponds and prepare construction documents. The regional ponds will reduce flooding downstream and will reduce the size requirements for the Marumsco Creek Channelization. (Revised end date pending funding.) At this time the cost to complete this project is undetermined.
Project Manager: Mark Colwell     send an email
Alternate Manager: Madan Mohan     
Agency Name: Department of Public Works - Environmental Services QPR?: Yes
Magisterial District: Occoquan
Original Budget: $1,800,000.00

Revised Budget:

---
Original Start Date: 3/1/1985

Revised Start Date:

Original End Date: 6/30/2002

Revised End Date:

6/30/2015
Last Updated On: 2/29/2016 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. Capital Improvement Project - Marumsco Creek

$1,800,000.00 $1,500,000.00
       
Total Amount: $1,800,000.00 $1,500,000.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
   
1. Study 3/1/1985 3/1/1987    
2. Preliminary design 8/1/1991 1/1/1992    
3. Final design of Pond 1 (Original Start Date and End Date to be determined.)    
4. Construction of Pond 1 (Original Start Date and End Date to be determined.)    
5. Final design of Pond 2 5/1/2000 6/1/2000    
6. Construction of Pond 2 6/1/2000 6/30/2002 8/30/2003    


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue