Project Detail
Project Main Menu

Project Overview
Project Name: ES: Lake Ridge Section 14K / Watershed: Occoquan River
Project Type: SWM Facilities Access & Access Easement Acquisition
Project Description: (Lake Ridge [SD89-70R], Near the end of Hedges Run Drive) This project includes the processing of an entrance easement and the construction of an access road to the existing SWM pond No. 120, which is maintained by the Department of Public Works.
Project Manager: Khalid Quraishi     send an email
Alternate Manager: Mukesh Patel     
Agency Name: Department of Public Works - Environmental Services QPR?: Yes
Magisterial District: Occoquan
Original Budget: $25,000.00

Revised Budget:

$25,000.00
Original Start Date: 7/1/2002

Revised Start Date:

7/1/2002
Original End Date: 12/30/2003

Revised End Date:

2/27/2004
Last Updated On: 8/30/2004 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. Storm Water Management Fund

$25,000.00 ---
       
Total Amount: $25,000.00 $25,000.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
   
1. Right of Entry 7/1/2002 11/15/2002    
2. Survey 1/15/2003 2/28/2003    
3. Design 3/15/2003 4/30/2003    
4. Easement Acquisition and Plat Preparation (Actual start date and end date to be determined.) 5/1/2003 6/30/2003    
5. Easement acquisition and plat recordation 7/1/2003 12/30/2003 2/27/2004    
6.    


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue
12/31/2003The offer made by the County for the "Quick Take" has been accepted by the property owner. The recordation of the easement is scheduled by 2/27/04.

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue