Project Name: ES: 16934-16950 Cass Brook Lane/Watershed: Powells Creek
Project Type: Drainage Improvement Project
Project Description: (River Oaks Section 1, Project Code Number: 5582) Storm water runoff is causing standing water, sogginess and basement flooding. Public Works will design and construct a drainage system that will alleviate the problem.
Project Manager: Khalid Quraishi     send an email
Alternate Manager: Mukesh Patel     
Agency Name: Department of Public Works - Environmental Services QPR?: Yes
Magisterial District: Woodbridge
Original Budget: $28,000.00

Revised Budget:

$28,000.00
Original Start Date: 3/1/2003

Revised Start Date:

4/1/2003
Original End Date: 7/30/2004

Revised End Date:

6/30/2005
Last Updated On: 9/28/2005 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. CIP

$28,000.00 ---
       
Total Amount: $28,000.00 $28,000.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
   
1. Right of Entry 4/1/2003 6/1/2003    
2. Preparation of Task Order & Field Survey 6/10/2003 8/15/2003    
3. Design 8/25/2003 8/29/2003    
4. Design approval by homeowners 9/3/2003 9/12/2003    
5. VDOT Land Use Permit 9/17/2003 10/24/2003    
6. Construction 11/4/2003 11/28/2003 12/30/2003    
7. Easement plat preparation and recordation 1/4/2004 4/30/2004 6/30/2005    


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue