Project Name: Fire and Rescue CIP - Birchdale Station Renovation
Project Type: Expansion reconfiguration remodeling in existing Fire and Rescue Station (Dale City VFD Station 10, 14998 Birchdale, Woodbridge, VA 22193)
Project Description: This project is proposed to replace the current Fire and Rescue station located at the intersection of Birchdale Avenue and Dale Boulevard. A new station is being constructed at the intersection of Dale Boulevard and Catalpa Court. The new station will be approximately 18,500 square foot with expanded office space, sleeping quarters, fitness area and more suitable apparatus areas.
Project Manager: Steven Kersse     send an email
Alternate Manager: Donna M. Poillucci     
Agency Name: QPR?: Yes
Magisterial District: Neabsco
Original Budget: $8,946,919.00

Revised Budget:

$8,997,269.00
Original Start Date: 7/1/2002

Revised Start Date:

Original End Date: 6/20/2003

Revised End Date:

2/1/2008
Last Updated On: 2/17/2010 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. Proffers

$58,918.00 $140,980.00 7/1/2006

2. Fire Levy

$4,189,666.00 $4,218,398.00 7/1/2006

3. Debt

$4,650,000.00 $4,600,000.00 7/1/2005

4. General Fund

$48,335.00 $37,891.00 7/1/2003
       
Total Amount: $8,946,919.00 $8,997,269.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
   
1. Planning & Design 7/1/2002 3/1/2004 6/30/2004 4/1/2006    
2. Construction 7/1/2004 5/1/2007 6/30/2006 2/1/2008    
3. Occupancy 1/1/2007 1/1/2007 2/1/2008    


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue
7/27/2005Land has been acquired at the intersection of Dale Blvd. and Catalpa Court and the project is now moving forward.
4/7/2005Land for the new station has been acquired in the area of Dale Blvd. and Benita Fitzgerald Drive.
11/13/2003DCVFD is researching land options.
8/25/2003DCVFD has determined that the current location of the "Birchdale Station" does not have enough land to support the needed facility. They are exploring alternate locations that are near the existing facility. Funding for land is not as yet in this project.

2. Schedule/Timing Issues     

 

Date

Issue
8/19/2009The new Station 10 is operational. Minor punch list items are still being taken care of.
4/15/2009On schedule and still looking at a spring opening.
11/10/2008Project is on time and within budget. Expected move in date is Spring of 2009.
4/15/2008Footers have been poured and drainage system is being installed. Construction is on schedule.
1/24/2008Site work has begun project has begun.
11/1/2007Construction to begin mid November.
8/13/2007Final set of plans to be sealed this month, expect start of construction early fall.
4/10/2007Site plan approval is expected to be compelted by May 2007. The Building permit is expeted to be submitted by June 2007 with and expected start of construction by August 2007. The construction contractor has been selected and is performing constructability review and value engineering analysis on the project.
1/22/2007Received first comments on Site submission #1 and had a post submission meeting Dec. 12. Working on Contractor selection. Drawings are at 60% at this point and are on target for late spring early summer start.
9/19/2006Hired design consultant and they are working on their plan submission and permitting
7/12/2006Design development is in the works and will be moving on into CD phase by August. Met with Catbrier HOA on June 17th at their annual meeting. The project was well received by the HOA-Sup. Jenkins was in attendance.

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue