Project Name: Fire and Rescue CIP - Antioch Road
Project Type: New Fire and Rescue Station
Project Description: The Antioch Road Fire and Rescue Station is approximately 18,400 square foot station and is approved to be built at 5901 Antioch Road with gated access through the Dominion Valley Community. The station will be equipped with a pumper and an advanced life support (ALS) ambulance and basic life support (BLS)ambulance. Career personnel staffing is proposed as a 24 hour pumper and 24 hour medic unit.
Project Manager: Steven Kersse     send an email
Alternate Manager: Donna M. Poillucci     
Agency Name: Fire and Rescue QPR?: Yes
Magisterial District: Gainesville
Original Budget: $11,486,730.00

Revised Budget:

$8,296,207.00
Original Start Date: 7/1/2003

Revised Start Date:

Original End Date: 1/31/2008

Revised End Date:

Last Updated On: 11/10/2011 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. Proffers/General Fund - FY 2008

$272,500.00 --- 7/1/2007

2. Proffers Projected - FY 2007

$74,615.00 --- 7/1/2006

3. Debt - FY 2007

$5,355,000.00 --- 7/1/2006

4. Proffers/Genreal Fund

$244,410.00 --- 7/1/2005

5. Fire and Rescue Levy - FY 2005 through 2008

$5,470,806.00 $2,280,283.00 7/1/2004

6. Proffers - Prior Years

$69,399.00 --- 7/1/2003
       
Total Amount: $11,486,730.00 $8,296,207.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
   
1. Planning 7/1/2003 6/30/2006    
2. Design 7/1/2004 6/30/2006 10/30/2006    
3. Construction 7/1/2006 12/31/2007    
4. Occupancy 1/1/2008 1/31/2008    


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue
11/16/2010Site easement has been approved by BOCS, moving along to get final.
8/24/2010Site easement has been negotiated and will head to the BOCS for approval.
2/16/2010Having issues with design of roof, working with architect to resolve issues.
2/11/2009The Antioch Fire and Rescue Station is operational. There are a few minor punch list items to remain.
8/4/2006It was determined that the alternative site was not good due to Environmental tests.
3/27/2006Current planned site is being evaluated for adequate service delivery needs. No impact on the opening of the facility has been determined as of this time.
8/19/2003Occupancy of the facility is scheduled for January 2008 (FY 2008),

2. Schedule/Timing Issues     

 

Date

Issue
8/19/2009Some building issues are being evaluated with the architect and building contractor. Still working on punch list items.
11/10/2008Construction is moving along without interruption and anticipated move in date is 12/1/2008
4/15/2008Slab has been poured. Steel supports are currently going up and roof is expected to be on next week.
1/24/2008Site work has begun. Footers have been poured and they are working on getting ready to pour the slab.
8/13/2007Relocation of Novec easement has been approved and work should begin in 2-8 weeks. Construction contract is going out to bid and project is moving along.
1/22/2007This project is moving forward, plans were submitted to planning for a 2nd review. Chief Bird has met with Novec to have power line moved on the property.
8/4/2006Original site plans have been taken off hold and are in the process of being reviewed. This project is proceeding forward with the original proffered site.
7/12/2006A new site being evaluated, this could delay the project by 6 months.

3. Fiscal/Resource Issues     

 

Date

Issue
8/13/2007VRA Loan was completed and submitted.
8/19/2003Career staff will be hired in FY 2008.

4. Impact on Other Projects     

 

Date

Issue