Project Detail
Project Main Menu

Project Overview
Project Name: Fire and Rescue CIP - River Oaks Station
Project Type: New Fire and Rescue Station
Project Description: This project is intended to replace the Newport Station identified in the FY 02-07 CIP, as well as a proposed proffered site for a station on Cherry Hill Road. A comprehensive station location study was conducted in 2000 which recommended co-locating these two stations into one. The River Oaks Fire and Rescue Station will be located near the intersection of River Ridge Blvd. and Jefferson Davis Highway (Route 1) and will be approximately 25,000 square feet. The station will be equipped with a pumper, tanker, recue squad, basic life support (ambulance), and an advanced life support (ALS) ambulance. Volunteer fire protection will be provided by the Dumfries-Triangle Volunteer Fire Department while emergency medical services will be provided by the Dumfries-Triangle Rescue Squad. Career personnel staffing is proposed to be a 24 hour medic unit and a daytime pumper.
Project Manager: Steven Kersse     send an email
Alternate Manager: Donna M. Poillucci     
Agency Name: Fire and Rescue QPR?: Yes
Magisterial District: Woodbridge
Original Budget: $3,251,002.00

Revised Budget:

$11,172,344.00
Original Start Date: 7/1/2002

Revised Start Date:

Original End Date: 1/31/2006

Revised End Date:

7/1/2008
Last Updated On: 11/10/2011 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. Fire and Rescue Levy

$594,624.00 $5,268,707.00 7/1/2005

2. Debt (VRA)

$2,600,000.00 $5,265,909.00 7/1/2004

3. Proffers/General Fund

$56,378.00 $637,728.00 7/1/2002
       
Total Amount: $3,251,002.00 $11,172,344.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
   
1. Planning 7/1/2002 6/30/2003    
2. Land Acquisition 7/1/2002 7/1/2002 6/30/2003 7/1/2004    
3. Design 7/1/2003 7/1/2004 6/30/2004 7/1/2006    
4. Construction 7/1/2004 9/1/2006 1/31/2006 6/1/2008    
5. Occupancy 1/1/2006 1/31/2006 7/1/2008    


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue
11/16/2010Station up and running. Have minor punch items remaining.
8/24/2010Grand Opening scheduled for Sept. 11, 2010. Working on punch list items.
4/9/2010Project on-time and moving along.
2/16/2010Project is on time and moving along. Exterior of building is mostly completed inlcuding landscaping. Working on interior buid out.
8/19/2009Project is running on schedule. Building is under roof, brick work is almost complete and systems are being installed.
2/11/2009Site work is on schedule and footers are being poured.
11/10/2008Site work has begun. Anticipated project completion date is Spring 2010.
9/8/2008Received and are reviewing contractors bids. Expect award of contract with a week.
4/15/2008Offer letters have been sent for the easement purchases. The site plan has been approved. Expecting to have construction bid within the next couple of months.
1/24/2008County attorney's office is working on getting estimates on the easements needed for this project. Site plan has been resubmitted with new storm water management system in place. Project moving forward.

3. Fiscal/Resource Issues     

 

Date

Issue
7/27/2005Land has been acquired at the intersection of Jeff Davis Highway and River Ridge Blvd. Design work is now underway.
4/7/2005The BOCS authorized the condemnation of 5.7 acres located at the southeast corner of Jeff Davis Highway and River Ridge Blvd. The Certificate of Taking was executed on 2/1/2005.
12/1/2003The piece of land identified two years ago is no longer available. Alternative sites in the area are currently being explored
8/20/2003The identified piece of land for this project has not yet been purchased and there is question regarding the continued availability of the negotiated price (negotiations were done approximately two years ago.) If the negotiated price is no longer available there could be significant impact on the project budget that is currently unknown.