Project Detail
Project Main Menu

Project Overview
Project Name: DOT: James Madison Highway (Route 15)
Project Type: 2002 Road Bond Project
Project Description: This project was divided into two sections, a northern section and southern section. Both sections will create a four-lane divided facility with median that will widen approximately 19,639 linear feet of Route 15. The northern section will widen Route 15 north of Dominion Valley to the intersection of Route 234. This section will include the realignment of Route 234 & Waterfall Road to create one intersection with Route 15. The southern section will widen Route 15 from north of Route 66 to north of Utterback Lane. Improvements will also include extending Heathcote Blvd. from its intersection with Rt. 15 east to its existing intersection with Old Carolina Rd, and widening Old Carolina Rd. from Heathcote Blvd. north to the existing Old Carolina widened section.
Project Manager: Khattab O. Shammout     send an email
Alternate Manager: Thomas J. Blaser     
Agency Name: Department of Transportation QPR?: Yes
Magisterial District: Gainesville
Original Budget: $18,304,126.00

Revised Budget:

$22,499,825.00
Original Start Date: 7/1/2003

Revised Start Date:

Original End Date: 6/30/2006

Revised End Date:

12/15/2009
Last Updated On: 2/1/2010 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. Proffer Contributions

$880,132.00 --- 7/1/2006

2. Proffer Funds - Contributions

$0.00 $219,755.00 7/1/2005

3. Proffer Funds - Contributions

$0.00 $883,280.00 7/1/2004

4. 2002 Road Bond Proceeds

$16,540,714.00 $19,772,922.00 7/1/2004

5. Proffer Funds - Contributions

$883,280.00 $743,736.00 7/1/2003
       
Total Amount: $18,304,126.00 $22,499,825.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
   
1. Phase I - Northern Section, Design - Build 2/20/2007 12/15/2009    
2. Phase II, Southern Section - Design/Engineering 7/1/2003 3/1/2005 12/1/2005 7/30/2007    
3. Phase II, Southern Section - Right-of-Way 7/1/2004 4/1/2006 9/30/2004 6/5/2007    
4. Phase II, Southern Section - Utility Relocation 10/1/2004 6/1/2006 12/31/2004 10/31/2007    
5. Phase II, Southern Section - Construction 4/1/2005 12/5/2006 8/1/2006 12/14/2009    
6. Phase III - Heathcote Blvd., Design - Build 2/20/2007 7/31/2008 10/31/2008    
7. Phase IV, Old Carolina Rd., Design - Build 2/20/2007 7/1/2009 9/1/2009    
8. Phase V - Waterfall Realignment, Design - Build 2/20/2007 6/30/2008 9/15/2008    


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue