Project Detail
Project Main Menu

Project Overview
Project Name: TD: University Blvd
Project Type: Innovation @ Prince William
Project Description: Project consists of constructing approximately 1,700 linear feet of three lanes of a future six-lane divided facility with raised median and pedestrian facilities. Also included is a 30 inch waterline that runs along the project, crosses Route 234 and continues for 900 feet east of Route 234 Bypass.
Project Manager: Thomas J. Blaser     send an email
Alternate Manager: Khattab O. Shammout     
Agency Name: Transportation Division of Public Works QPR?: Yes
Magisterial District: Brentsville
Original Budget: $2,173,367.00

Revised Budget:

$2,184,367.00
Original Start Date: 7/1/2002

Revised Start Date:

Original End Date: 12/31/2004

Revised End Date:

Last Updated On: 11/15/2004 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. Innovation @ Prince William Land Sales and General Fund Carryover

$2,069,367.00 $2,080,367.00 7/1/2004

2. Innovation @ Prince William Land Sales and General Fund Carryover

$104,000.00 --- 7/1/2002
       
Total Amount: $2,173,367.00 $2,184,367.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
   
1. Design 7/1/2002 8/1/2003 10/1/2003    
2. Construction 10/7/2003 12/31/2004 9/30/2004    


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue