Project Name: DOT: PW Parkway Intersection with Minnieville Road
Project Type: 2002 Road Bond
Project Description: The project consists of intersection improvements at the intersection of Prince William Parkway and Minnieville Road in accordance with the approved plans. The improvements include the widening of approximately 2800’ LF of westbound Prince William Parkway in the vicinity of Minnieville Road. The widening is intended to accommodate an additional westbound left turn lane for a total of three left turn lanes, an additional westbound through lane, signal adjustment to accommodate the new improvements, and surface overlay of the improved westbound project area.
Project Manager: Khattab O. Shammout     send an email
Alternate Manager: Thomas J. Blaser     
Agency Name: Department of Transportation QPR?: Yes
Magisterial District: Neabsco
Original Budget: $2,525,213.00

Revised Budget:

$2,565,000.00
Original Start Date: 7/1/2003

Revised Start Date:

12/23/2003
Original End Date: 6/30/2005

Revised End Date:

7/27/2007
Last Updated On: 9/23/2008 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. 2002 Road Bond

$2,525,213.00 $2,565,000.00 7/1/2003
       
Total Amount: $2,525,213.00 $2,565,000.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
   
1. Design/Engineering 1/5/2004 4/1/2004 10/1/2004 4/15/2006    
2. Right-of-Way Acquisition 2/1/2004 2/28/2005 2/29/2004 4/30/2006    
3. Utility Relocation 2/1/2004 4/28/2006 8/15/2004 10/26/2006    
4. Advertise for Construction 5/1/2004 7/12/2006 6/1/2004 8/8/2006    
5. Construction 6/1/2004 10/3/2006 9/30/2004 7/27/2007    


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue
2/25/2007ShOP Drawing for the traffic signal was approved by VDOT

2. Schedule/Timing Issues     

 

Date

Issue
4/5/2007Traffic will be switched after signal installation to work on the median