Project Detail
Project Main Menu

Project Overview
Project Name: TD: Ridgefield Road
Project Type: 1998 Road Bond Project
Project Description: Ridgefield Road a 1.5 mile four lane divided roadway was completed and opened to traffic on October 31, 2002. It is providing an alternative connection to the Prince William Parkway from Dale Boulevard. It is relieving traffic on Hillendale Drive.
Project Manager: Thomas J. Blaser     send an email
Alternate Manager: Khattab O. Shammout     
Agency Name: Transportation Division of Public Works QPR?: Yes
Magisterial District: Coles, Neabsco
Original Budget: $6,299,121.00

Revised Budget:

$7,828,575.00
Original Start Date: 7/1/1999

Revised Start Date:

Original End Date: 10/31/2002

Revised End Date:

Last Updated On: 4/26/2004 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. November 1998 County Road Bond

$6,274,121.00 --- 7/1/1999

2. Proffers

$25,000.00 ---

3. Developer Agreement - KSI

$0.00 $1,414,644.00

4. Developer Agreement - VA Water Co.

$0.00 $114,810.00
       
Total Amount: $6,299,121.00 $7,828,575.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
   
1. Design 12/1/1999 7/15/2001    
2. Right of Way Acquisition 6/1/2001 8/31/2001    
3. Utility Relocation 6/1/2001 11/30/2001    
4. Construction 10/1/2001 10/31/2002    


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue