Project Detail
Project Main Menu

Project Overview
Project Name: ES: 12024 Cardamom Drive / Watershed: Occoquan River
Project Type: Drainage Improvement Project
Project Description: Storm water runoff is causing erosion along a ditch in a common area that extends through the backyard of the apartment complex. Public Works will design an erosion control measure to prevent erosion.
Project Manager: Khalid Quraishi     send an email
Alternate Manager: Mukesh Patel     
Agency Name: Department of Public Works - Environmental Services QPR?: Yes
Magisterial District: Brentsville, Occoquan
Original Budget: $45,000.00

Revised Budget:

$45,000.00
Original Start Date: 4/5/2004

Revised Start Date:

Original End Date: 12/23/2004

Revised End Date:

Last Updated On: 11/15/2004 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. CIP

$45,000.00 ---
       
Total Amount: $45,000.00 $45,000.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
   
1. Right of Entry 4/5/2004 8/20/2004    
2. Survey 6/15/2004 7/30/2004    
3. Design 6/28/2004 9/30/2004    
4. Construction 11/1/2004 12/23/2004    


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue