Project Name: DOT: Spriggs Road Improvements-Phase I
Project Type: 1998 County Road Bond
Project Description: The Spriggs Road Improvement Project-Phase I will include widening and improving the existing two (2) lane facility to a four (4)lane divided roadway with five (5) foot concrete sidewalk and eight (8) foot asphalt trail divided roadway between Minnieville Road (Route 640) and Dumfries Road (Route 234). The project will include improving the current alignment by removing sharp curves and moving its intersection with Route 234 west of its current location. The project also includes the improvement and flattening the curve on Minnieville Road south of Spriggs Road. The contract completion date was extended to April 28, 2006.
Project Manager: Khattab O. Shammout     send an email
Alternate Manager: Thomas J. Blaser     
Agency Name: Department of Transportation QPR?: Yes
Magisterial District: Coles, Potomac
Original Budget: $17,635,497.00

Revised Budget:

$19,871,243.00
Original Start Date: 7/1/1999

Revised Start Date:

Original End Date: 5/30/2005

Revised End Date:

4/28/2006
Last Updated On: 9/18/2008 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. November 1998 County Road Bond $19

$17,295,000.00 $17,141,931.00 7/1/2004

2. Expenditure Reimbursement

$39,943.00 $140,320.00 5/18/2004

3. Proffers

$288,954.00 $868,369.00 7/1/2002

4. Rental Income

$11,600.00 $6,000.00 7/1/2002

5. Transfer From Capital Projects Fund

--- $1,714,623.00
       
Total Amount: $17,635,497.00 $19,871,243.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
   
1. Design 12/5/2000 9/30/2002 11/15/2004    
2. Utility Relocation 12/1/2002 5/30/2003 3/30/2004    
3. Right-of-way acquisition 10/1/2001 1/31/2003 4/30/2003 11/30/2004    
4. Construction 5/1/2003 1/5/2004 5/30/2005 4/28/2006    


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue