Project Detail
Project Main Menu

Project Overview
Project Name: ES: Cabin Run Lower Stream Restoration-Quantico Creek Tributary/Watershed: Quantico Creek
Project Type: Drainage Improvement Project
Project Description: (Project Code Number: 5608). The existing stream channel is contributing to a flooding problem. The County will design and construct a new stream channel that is further away from the properties and will connect to the existing creek. This improvement will handle a 2-year storm event.
Project Manager: Thomas E. Dombrowski     send an email
Alternate Manager: Charles B. Williamson     
Agency Name: Department of Public Works - Environmental Services QPR?: Yes
Magisterial District: Potomac
Original Budget: $330,000.00

Revised Budget:

$360,000.00
Original Start Date: 1/15/2004

Revised Start Date:

Original End Date: 3/1/2006

Revised End Date:

6/30/2016
Last Updated On: 1/15/2013 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. CIP

$30,000.00 $60,000.00

2. Construction

$300,000.00 ---
       
Total Amount: $330,000.00 $360,000.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
Assigned
Staff
Number
of Hours
1. Right of Entry 1/15/2004 3/15/2004 4/15/2005
2. Preparation of Task Order & Field Survey 3/16/2004 6/30/2004 2/28/2006
3. Preparation of Task Order for Wetland Delineation, & Design of Channel Improvement. 8/17/2004 2/28/2006 9/17/2004 8/31/2006
4. Design approval by homeowners 9/20/2004 10/15/2004
5. Fund allocation 10/18/2004 9/29/2006 11/15/2004 2/28/2007
6. Material purchase (contingent upon funding) 11/29/2004 2/28/2007 12/30/2004 4/13/2007
7. Task order to PSA for conceptual design of channel realignment issued ($33K). 12/30/2006 12/31/2007
8. Construction (contingent upon funding) 1/1/2006 4/13/2007 3/1/2006 6/30/2008
9. Review and redesign the engineering plans for the stream segment 11/30/2009 2/15/2010 12/31/2009 4/30/2010
10. Preparation of permit application to be submitted to USCOE. 1/7/2011 4/15/2011 TED
11. Stream Restoration Monitoring and Report submitted annual report to USACOE. 1/15/2004 6/30/2012 6/30/2016 TED 40


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue
1/1/2006The area of concern is a flood plain with RPA, which will require wetland delineation and permission at the state and federal levels.

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue