Project Detail
Project Main Menu

Project Overview
Project Name: PM: McCoart Backfill
Project Type: Building and Office Renovations
Project Description: The McCoart Backfill involves the allocation and occupancy of space vacated by agencies moving to the Phase III Administrative Building. Also, a new entrance and corridor are to be constructed at the rear of the building.
Project Manager: Timothy G. Moore     send an email
Alternate Manager: Martha A. Clark     
Agency Name: Public Works QPR?: Yes
Magisterial District: Coles
Original Budget: $2,100,000.00

Revised Budget:

$1,980,000.00
Original Start Date: 8/16/2004

Revised Start Date:

Original End Date: 12/30/2006

Revised End Date:

3/31/2009
Last Updated On: 11/18/2009 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. CIP Funding

$2,100,000.00 $1,980,000.00
       
Total Amount: $2,100,000.00 $1,980,000.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
   
1. Facility Programming & Block Plans 8/16/2004 8/1/2005 8/1/2005    
2. Construction Drawings 8/2/2005 8/2/2006 1/2/2006 4/13/2007    
3. Plans Review 3/1/2006 4/16/2007 3/31/2006 9/21/2007    
4. IFB / Bidding 1/3/2006 11/30/2007 2/3/2006 12/21/2007    
5. Board Agenda & Contract Award 2/3/2006 1/8/2008 2/28/2006 1/11/2008    
6. Construction, Renovations, Occupancy 4/1/2006 2/4/2008 12/30/2007 3/31/2009    


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue