Project Detail
Project Main Menu

Project Overview
Project Name: SW: Western Citizen Convenience Center Expansion
Project Type: Landfill CIP Project
Project Description: The project includes all work necessary to design and construct an expansion of the Western Citizen Convenience Center at the Balls Ford Road Yard Waste Compost Facility.
Project Manager: Sadhu S. Sandhu     send an email
Alternate Manager: Thomas J. Smith     
Agency Name: QPR?: Yes
Magisterial District: Brentsville
Original Budget: $941,325.00

Revised Budget:

$896,078.00
Original Start Date: 7/18/2005

Revised Start Date:

12/1/2005
Original End Date: 9/30/2006

Revised End Date:

6/1/2008
Last Updated On: 11/14/2008 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. Construction Management -Solid Waste Fees

$60,000.00 $0.00 7/1/2005

2. Construction - Solid Waste Fees

$788,925.00 $821,546.00 7/1/2005

3. Design - Solid Waste Fees

$92,400.00 $74,532.00 7/1/2004
       
Total Amount: $941,325.00 $896,078.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
   
1. Design 12/1/2005 12/31/2005 8/2/2006    
2. Invitation for Bid 12/31/2005 2/15/2007 3/31/2006 6/30/2007    
3. Construction 4/1/2006 7/1/2007 9/30/2006 6/1/2008    


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue
6/16/2008Final completion of the project was 6/1/08 and the facility was opened to citizens on 6/16/08.

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue