Project Detail
Project Main Menu

Project Overview
Project Name: ES: 13244 Putnam Circle (Greenwich Hill)/Watershed: Marumsco Creek
Project Type: Drainage Improvement Project
Project Description: (Marumsco Village, Section 4, Project Code Number: 5647) Storm water runoff is causing standing water on the street. Public Works will inspect, clean the storm drain systems, repair the concrete V-ditch and stabilize the eroded areas.
Project Manager: Khalid Quraishi     send an email
Alternate Manager: Mukesh Patel     
Agency Name: Department of Public Works - Environmental Services QPR?: Yes
Magisterial District: Woodbridge
Original Budget: $25,000.00

Revised Budget:

$25,000.00
Original Start Date: 3/31/2005

Revised Start Date:

Original End Date: 6/30/2005

Revised End Date:

Last Updated On: 9/28/2005 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. Storm Drain Major Maintenance

$25,000.00 ---
       
Total Amount: $25,000.00 $25,000.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
   
1. Right of Entry 3/31/2005 4/15/2005    
2. Inspection of storm drain system, replacement of manhole cover 4/15/2005 6/15/2005 5/5/2005    
3. Repair of V-ditch and stabilize the eroded area 5/15/2005 6/30/2005    
4.    
5.    
6.    
7.    


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue