Project Name: ES: 9550 Birmingham Drive/Watershed: Bull Run
Project Type: Drainage Improvement Project
Project Description: (Buckhall, Project Code Number: 5652) Storm water runoff is causing standing water, sogginess and backyard flooding. Public Works will design and construct a drainage system to minimize the problem.
Project Manager: Khalid Quraishi     send an email
Alternate Manager: Mukesh Patel     
Agency Name: Department of Public Works - Environmental Services QPR?: Yes
Magisterial District: Brentsville
Original Budget: $15,000.00

Revised Budget:

$15,000.00
Original Start Date: 6/1/2005

Revised Start Date:

Original End Date: 12/30/2005

Revised End Date:

Last Updated On: 4/6/2006 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. CIP

$15,000.00 ---
       
Total Amount: $15,000.00 $15,000.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
   
1. Right of Entry 6/1/2005 6/30/2005    
2. Field Survey 6/30/2005 9/30/2005    
3. Design & its Approval by the homeowner 9/30/2005 10/14/2005    
4. VDOT Land Use Permit 10/14/2005 11/30/2005    
5. Material Purchase & Installation of Pipe 11/30/2005 12/30/2005    
6.    


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue