Project Name: ES: Phase I of Orange Street/Watershed: Quantico Creek
Project Type: Drainage Improvement Project
Project Description: The project scope is to clean, improve, and stabilize the drainage ditch. The project will also minimize the creek erosion in order to protect the impacted properties.
Project Manager: Khalid Quraishi     send an email
Alternate Manager: Mukesh Patel     
Agency Name: Department of Public Works - Environmental Services QPR?: Yes
Magisterial District: Potomac
Original Budget: $20,000.00

Revised Budget:

$20,000.00
Original Start Date: 9/15/2004

Revised Start Date:

Original End Date: 1/30/2005

Revised End Date:

Last Updated On: 2/16/2011 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. CIP

$20,000.00 ---
       
Total Amount: $20,000.00 $20,000.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
   
1. Right of Entry 9/15/2004 9/30/2004    
2. Design 9/30/2004 10/2/2004    
3. Meeting with homeowners and their approval 10/5/2004 10/13/2004    
4. Construction (Phase 1 - near Old Triangle Road) 11/15/2004 1/11/2005    


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue