Project Name: FC: Western District Police Station
Project Type: New Facility Construction
Project Description: Western District Police Station is a 50,013 square foot facility that will provide space for police officers, storage space for officers, evidence storage processing area, interview rooms and a community space for public meetings.
Project Manager: Mohamed E. Abdelrahim     send an email
Alternate Manager: LouAnn D. Purkins     
Agency Name: Department of Public Works QPR?: Yes
Magisterial District: Brentsville
Original Budget: $16,618,207.00

Revised Budget:

$21,471,120.00
Original Start Date: 1/1/2000

Revised Start Date:

Original End Date: 8/1/2004

Revised End Date:

8/8/2006
Last Updated On: 1/18/2007 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. Debt Funding

$16,618,207.00 $21,471,120.00
       
Total Amount: $16,618,207.00 $21,471,120.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
   
1. Planning (Programming and Schematic Design) 1/1/2000 10/1/2000    
2. RFP for Architectural Services 10/1/2000 7/1/2001    
3. A/E Contract Award 2/1/2002 2/1/2002 4/2/2002    
4. Design Development and Construction Documents 2/1/2002 7/17/2002 12/2/2002 4/28/2003    
5. Permit Review 1/1/2003 7/10/2003 3/1/2003 10/24/2003    
6. Bidding 3/1/2003 4/5/2004 4/1/2003 5/4/2004    
7. Construction 4/1/2003 6/1/2004 7/1/2004 1/30/2006    
8. Punchlist 7/1/2004 1/30/2006 8/1/2004 2/28/2006    
9. Occupancy 8/1/2004 3/15/2006 3/15/2006 8/8/2006    


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue