Project Overview
Project Name: DOT: Fuller Heights Road Sidewalk
Project Type: TRIP Funds - Sidewalk Construction
Project Description: Provide a sidewalk, curb and gutter on the north side of Fuller Heights Road (Route 619) from Bethlehem Church Road to 0.23 miles east of Mockingbird Heights Road (Route 613).
Project Manager: Khattab O. Shammout     send an email
Alternate Manager: Kafayat U. Rahmani     
Agency Name: Department of Transportation QPR?: Yes
Magisterial District: Potomac
Original Budget: $400,000.00

Revised Budget:

$400,000.00
Original Start Date: 10/31/2008

Revised Start Date:

Original End Date: 8/31/2011

Revised End Date:

Last Updated On: 9/24/2013 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. FY08 TRIP Funds Allocated

$400,000.00 --- 2/28/2008
       
Total Amount: $400,000.00 $400,000.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
   
1. Engineering Design 10/31/2008 4/14/2010 6/30/2009 1/12/2011    
2. Right-of-way/Easements Acquisition 1/1/2010 11/16/2010 6/30/2010 5/31/2011    
3. Relocation of Utilities 7/1/2010 10/1/2010 12/31/2010 12/31/2010    
4. Construction 1/1/2011 6/1/2011 8/31/2011    


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue