Project Name: ES: 1908 Radford Drive/Watershed: Marumsco Creek
Project Type: Drainage Improvement Project
Project Description: (Project Code Number: 5678). The property owner is experiencing a drainage problem in their yard. The County will design and install a French drain system to carry the runoff to the nearby VDOT structure.
Project Manager: Khalid Quraishi     send an email
Alternate Manager: Mukesh Patel     
Agency Name: Department of Public Works - Environmental Services QPR?: Yes
Magisterial District: Woodbridge
Original Budget: $20,000.00

Revised Budget:

$30,000.00
Original Start Date: 10/14/2005

Revised Start Date:

Original End Date: 7/31/2006

Revised End Date:

12/29/2006
Last Updated On: 2/15/2007 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. CIP

$20,000.00 $30,000.00
       
Total Amount: $20,000.00 $30,000.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
   
1. Right of Entry 10/14/2005 12/31/2005    
2. Field Survey 12/31/2005 4/15/2006    
3. Design, and property owner's approval 4/15/2006 5/10/2006    
4. VDOT Land Use Permit 5/10/2006 6/23/2006 8/31/2006    
5. Material purchase 6/23/2006 8/31/2006 7/15/2006 10/25/2006    
6. Installation of storm drain pipe system 7/15/2006 10/25/2006 7/31/2006 12/29/2006    
7.    


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue