Project Detail
Project Main Menu

Project Overview
Project Name: PM: Fleet Heavy Equipment Shop Renovations
Project Type: Construction
Project Description: Replacing segments of the existing deteriorated concrete slab with new impact absorbing composite flooring made of steel checkered plates embedded in concrete slab on grade. Raise existing overhead doors and install a new ventilation system
Project Manager: Said G. Said     send an email
Alternate Manager: Martha A. Clark     
Agency Name: Public Works, Property Mgmt. QPR?: Yes
Magisterial District: Coles
Original Budget: $350,000.00

Revised Budget:

$640,000.00
Original Start Date: 10/28/2005

Revised Start Date:

10/28/2005
Original End Date: 11/10/2006

Revised End Date:

12/15/2006
Last Updated On: 11/5/2007 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. Approved FY05 carryover $350000

$350,000.00 --- 8/5/2006

2. BOCS approved transfer of $290000 from Solid Waste and Fleet Budgets to cover the shortage in the project's budget

--- $290,000.00 6/6/2006
       
Total Amount: $350,000.00 $640,000.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
Assigned
Staff
 
1. Plans review by PW Building Development 12/6/2005 1/25/2006 SGS  
2. Invitation for Bid/ bid opening 3/27/2006 4/20/2006 PM  
3. Board Agenda, Budget Transfer and Contract Award 5/24/2006 6/6/2006 SGS& Purchasing  
4. Procurement of materials 6/28/2006 8/8/2006 SGS  
5. Construction Work 8/14/2006 11/17/2006 MG  


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue