Project Detail
Project Main Menu

Project Overview
Project Name: PM: Fleet Shop Air-Conditioning System
Project Type: Construction
Project Description: Install new Air-Conditioning Systems for the Fleet Shop and Parts Room
Project Manager: Said G. Said     send an email
Alternate Manager: Martha A. Clark     
Agency Name: Public Works, Property Mgmt. QPR?: Yes
Magisterial District: Coles
Original Budget: $271,000.00

Revised Budget:

$271,000.00
Original Start Date: 9/29/2005

Revised Start Date:

Original End Date: 9/14/2006

Revised End Date:

10/24/2006
Last Updated On: 4/5/2007 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. FY 05 Carryovers

$271,000.00 --- 8/23/2005
       
Total Amount: $271,000.00 $271,000.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
Assigned
Staff
 
1. A/C System Design 1/11/2006 3/15/2006 SGS & A/E  
2. Plans review By PW Building Development 3/15/2006 3/21/2006 PW  
3. Invitation For Bid & Bid opening 5/1/2006 5/23/2006 BD  
4. Board Agenda and Contract Award by BOCS 5/24/2006 6/27/2006 SGS & Purchasing  
5. Installation of A/C Systems and Controls 8/1/2006 9/14/2006 MG  


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue