Project Detail
Project Main Menu

Project Overview
Project Name: ES: 907 Burke Drive/Watershed: Marumsco Creek
Project Type: Drainage Improvement Project
Project Description: (Project Code Number: 5687) Storm water runoff is causing standing water, sogginess and back yard flooding. Public Works will design and construct a drainage system to alleviate the problem.
Project Manager: Khalid Quraishi     send an email
Alternate Manager: Mukesh B. Patel     
Agency Name: Department of Public Works - Environmental Services QPR?: Yes
Magisterial District: Woodbridge
Original Budget: $20,000.00

Revised Budget:

---
Original Start Date: 5/31/2006

Revised Start Date:

Original End Date: 3/30/2007

Revised End Date:

9/28/2007
Last Updated On: 7/19/2007 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. CIP

$20,000.00 ---
       
Total Amount: $20,000.00 $20,000.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
   
1. Right of Entry 5/31/2006 8/31/2006 1/31/2007    
2. Preparation of Task Order & Field Survey (contingent upon right of entry agreemement from all impacted property owners) 8/31/2006 1/31/2007 10/31/2006 3/30/2007    
3. Design (contingent upon right of entry agreemement from all the impacted property owners) 10/31/2006 3/30/2007 11/30/2006 5/18/2007    
4. Design approval by homeowners (contingent upon right of entry agreemement from all impacted property owners) 11/30/2006 5/18/2007 12/29/2006 6/15/2007    
5. Material Purchase(contingent upon design approval from all impacted property owners) 12/29/2006 6/15/2007 2/16/2007 8/31/2007    
6. Construction (contingent upon design approval from all impacted property owners) 2/16/2007 8/31/2007 3/30/2007 9/28/2007    


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue
8/2/2006The right of entry agreements from the impacted property owners are in process.

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue