Project Name: ES: 18081 Possum Point Road/Watershed: Quantico Creek
Project Type: Drainage Improvement Project
Project Description: (Project Code Number: 5648) Storm water runoff is resulting in standing water, sogginess, and flooding in the back yard of the property. Public Works will design and construct a drainage system to alleviate the problem.
Project Manager: Khalid Quraishi     send an email
Alternate Manager: Mukesh B. Patel     
Agency Name: Department of Public Works - Environmental Services QPR?: Yes
Magisterial District: Potomac
Original Budget: $25,000.00

Revised Budget:

---
Original Start Date: 5/31/2006

Revised Start Date:

Original End Date: 12/29/2006

Revised End Date:

1/31/2007
Last Updated On: 7/19/2007 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. CIP

$25,000.00 ---
       
Total Amount: $25,000.00 $25,000.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
   
1. Right of Entry 5/31/2006 6/9/2006    
2. Meeting with the property owner 6/9/2006 6/16/2006    
3. Field Survey & Design 6/16/2006 9/29/2006    
4. Design approval by homeowners 9/28/2006 10/13/2006    
5. Material Purchase 10/13/2006 11/17/2006    
6. Construction 11/17/2006 12/29/2006 1/31/2007    


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date