Project Name: NS: Cardinal Drive Bradford Pears
Project Type: Bradford Pear trees
Project Description: The project consists of trees planted within the median areas along Cardinal Drive between Beavenwood and Swan Drive. The plantings will consist of Bradford Pears planted in alternate fashion.
Project Manager: Ed W. Wheeling     send an email
Alternate Manager: Liane Blake     
Agency Name: Neighborhood Services QPR?: Yes
Magisterial District: Potomac, Neabsco
Original Budget: $2,500.00

Revised Budget:

$2,500.00
Original Start Date: 8/20/2006

Revised Start Date:

Original End Date: 11/20/2006

Revised End Date:

12/20/2006
Last Updated On: 10/8/2014 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. (General Fund-Landscaping budgets)and Proffer Contributions. Plantings installed by inhouse staff at no cost.

--- ---
       
Total Amount: $0.00 $0.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
Assigned
Staff
 
1. Design 8/31/2006 9/14/2006 1  
2. VDOT permit 8/20/2006 10/20/2006 10/1/2006 11/1/2006 1  
3. VDOT permit approved 10/30/2006 11/1/2006 4  
4. Begin planting 12/4/2006 12/12/2006 4  
5. Planting complete 12/4/2006 12/12/2006 1  


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue