Project Overview
Project Name: DOT: Dale Boulevard Extension at Benita Fitzgerald Drive
Project Type:
Project Description: Extension of Dale Boulevard at its intersection with Benita Fitzgerald Drive to include the addition of dual left turn lanes at the intersection.
Project Manager: Thomas J. Blaser     send an email
Alternate Manager: Khattab O. Shammout     
Agency Name: Transportation QPR?: Yes
Magisterial District: Neabsco
Original Budget: $400,000.00

Revised Budget:

$515,000.00
Original Start Date: 2/1/2009

Revised Start Date:

Original End Date: 6/30/2010

Revised End Date:

8/31/2011
Last Updated On: 11/10/2011 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. Federal Funds

$400,000.00 $515,000.00 8/17/2009
       
Total Amount: $400,000.00 $515,000.00


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue