Project Detail
Project Main Menu

Project Overview
Project Name: DOT: Fuller Road/Fuller Heights Road Improvements
Project Type:
Project Description: This project will widen Fuller Road which is the entrance road serving the Quantico Marine Corps Base, the Town of Quantico, and communities adjacent to the base. The improvements will involve the widening of the existing four-lane undivided section to a four-lane divided section of roadway with improvements to the intersections of Route 1 and Fuller Heights Road.
Project Manager: Thomas J. Blaser     send an email
Alternate Manager: Khattab O. Shammout     
Agency Name: Transportation QPR?: Yes
Magisterial District: Potomac
Original Budget: $2,658,546.00

Revised Budget:

$2,658,546.00
Original Start Date: 5/19/2009

Revised Start Date:

Original End Date: 1/22/2010

Revised End Date:

9/30/2012
Last Updated On: 9/24/2013 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. State/Federal Funding

$2,658,546.00 --- 10/6/2009
       
Total Amount: $2,658,546.00 $2,658,546.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
   
1. Design 2/5/2010 7/31/2011    
2. R-O-W & Utility Relocation 8/1/2011 12/1/2011    
3. Construction 12/1/2011 9/30/2012    


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue