Project Name: ES: Andrew Leitch Park Stream Restoration: Neabsco Creek CIP
Project Type: Capital Improvement Project
Project Description: Restoration of over 1000 linear feet of Neabsco Creek in Andew Leitch Park in support for mitigation of stream impacts from the Route 15 Transportation Project.
Project Manager: Thomas E. Dombrowski     send an email
Alternate Manager: Charles B. Williamson     
Agency Name: Department of Public Works- Environmental Services Division QPR?: Yes
Magisterial District: Neabsco
Original Budget: $450,000.00

Revised Budget:

$450,000.00
Original Start Date: 11/21/2006

Revised Start Date:

Original End Date: 6/15/2015

Revised End Date:

Last Updated On: 2/16/2010 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. Funding provided by Transportation budget for mitigation of stream impacts from Route 15 project.

$450,000.00 --- 10/30/2008
       
Total Amount: $450,000.00 $450,000.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
Assigned
Staff
 
1. Completion of Segment I of Stream Restoration 6/10/2009 8/27/2009 PW-Construction Crew  
2. Completion of Segment II of Stream Restoration 9/1/2009 9/30/2009 PW- Construction Crew  
3. Completion of Segment III of Stream Restoration 10/1/2009 11/20/2009 PW-Construction Crew  


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue