Project Name: SW: Landfill Liner Design and Construction of Phase II, Cell A
Project Type: Landfill CIP Project
Project Description: The project includes all work necessary to design and construct the Phase II, Cell A lined landfill cell.
Project Manager: Sadhu S. Sandhu     send an email
Alternate Manager: Thomas J. Smith     
Agency Name: Public Works QPR?: Yes
Magisterial District: Coles
Original Budget: $6,800,000.00

Revised Budget:

$7,535,668.00
Original Start Date: 7/1/2009

Revised Start Date:

Original End Date: 12/31/2011

Revised End Date:

Last Updated On: 1/23/2012 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. Solid Waste Fees and Capital Reserve

$6,500,000.00 $7,235,668.00 7/1/2010

2. Solid Waste Fees/Capital Reserve

$300,000.00 $300,000.00 7/1/2009
       
Total Amount: $6,800,000.00 $7,535,668.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
   
1. Design 7/1/2009 4/30/2010    
2. Invitation for Bid 5/12/2010 7/1/2010    
3. Construction 7/21/2010 12/31/2011    


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue
7/1/2011Liner installation in the entire cell is completed. The contractor is placing gravel and installing the leachate collection system. Certification report for DEQ is being prepared and is scheduled to be submitted to DEQ by end of July 2011. Final completion of the cell is anticipated by September 2011.

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue