Project Name: SW: Landfill Cap Design and Construction of Phase I, Sequence 1
Project Type: Landfill CIP Project
Project Description: The project includes all work necessary to design and construct a final closure cap for Phase I, Sequence I (side slopes).
Project Manager: Sadhu S. Sandhu     send an email
Alternate Manager: Thomas J. Smith     
Agency Name: Public Works QPR?: Yes
Magisterial District: Coles
Original Budget: $5,250,000.00

Revised Budget:

$4,506,825.00
Original Start Date: 7/1/2009

Revised Start Date:

Original End Date: 12/31/2011

Revised End Date:

7/31/2012
Last Updated On: 1/10/2013 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. Solid Waste Fees/Closure Fund (Construction)

$5,000,000.00 $4,256,825.00 7/1/2010

2. Solid Waste Fees/Closure Fund (Design)

$250,000.00 $250,000.00 7/1/2009
       
Total Amount: $5,250,000.00 $4,506,825.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
   
1. Design 7/1/2009 5/1/2010    
2. Invitation for Bid (Neogotiate Contract) 5/12/2010 7/1/2010    
3. Construction 7/21/2010 12/31/2011 7/31/2012    


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue
1/9/2013Cap construction was completed on June 30, 2012. CQA certification report was prepared and submitted to DEQ on November 30, 2012 and the project is essentially complete.

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue