Project Detail
Project Main Menu

Project Overview
Project Name: ES: Pond (#51) Retrofit at Armstead Street/Marumsco Creek Watershed (New)
Project Type: Design, Construction and Easement Acquisition
Project Description: The County will design and construct pond retrofit.
Project Manager: Khalid Quraishi     send an email
Alternate Manager: Vakil A. Khan     
Agency Name: Public Works QPR?: Yes
Magisterial District: Neabsco
Original Budget: $25,000.00

Revised Budget:

$40,000.00
Original Start Date: 9/30/2009

Revised Start Date:

Original End Date: 12/31/2010

Revised End Date:

4/29/2011
Last Updated On: 11/10/2011 Maps  Pictures  Documents



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
   
1. Project recommendation by the consultants after the watershed study 9/30/2009 12/31/2009    
2. Field survey 12/31/2009 3/31/2010    
3. Design 3/31/2010 6/30/2010 7/30/2010    
4. Project Cost Estimate 6/30/2010 7/30/2010 7/30/2010 8/20/2010    
5. Construction & project completion 7/30/2010 1/3/2011 12/31/2010 4/29/2011    
6.    
7.    


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue