Project Name: DOT: Logmill Road Improvements (Parnell Court to Route 15)
Project Type: Roadway Improvement
Project Description: This project involves the improvement of a section of Logmill Road from the intersection with Route 15 to Parnell Court for an approximate distance of 1,600 linear feet.
Project Manager: Thomas J. Blaser     send an email
Alternate Manager: Khattab O. Shammout     
Agency Name: Transportation QPR?: Yes
Magisterial District: Gainesville
Original Budget: $2,970,000.00

Revised Budget:

$2,970,000.00
Original Start Date: 7/1/2011

Revised Start Date:

Original End Date: 11/30/2012

Revised End Date:

Last Updated On: 9/24/2013 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. Gainesville TRIP Funding

$270,000.00 --- 8/31/2011

2. Local Match

$270,000.00 --- 5/17/2011

3. Highway Safety Improvement Program (HSIP) Funding

$2,430,000.00 --- 5/17/2011
       
Total Amount: $2,970,000.00 $2,970,000.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
   
1. Design 7/1/2011 12/31/2011    
2. R-O-W & Utility Relocation 1/1/2012 2/28/2012    
3. Construction 3/1/2012 11/30/2012    


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue