Project Detail
Project Main Menu

Project Overview
Project Name: DOT: Prince William Parkway (Old Bridge Rd. to Minnieville Rd.)
Project Type: Design-Build Roadway Improvement
Project Description: The Prince William Parkway is designated to be a six lane divided roadway with a raised median. The project extends from existing Old Bridge Road to Minnieville Road. This project will be constructed in coordination with the intersection improvements at the Prince William Parkway and Hillendale Drive.
Project Manager: Thomas J. Blaser     send an email
Alternate Manager: Khattab O. Shammout     
Agency Name: Transportation QPR?: Yes
Magisterial District: Neabsco, Occoquan
Original Budget: $16,797,634.00

Revised Budget:

$16,797,634.00
Original Start Date: 9/15/2011

Revised Start Date:

Original End Date: 9/30/2014

Revised End Date:

Last Updated On: 9/24/2013 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. 2006 Bond Funding

$14,985,000.00 --- 7/1/2011

2. Local Proffer Funding

$1,812,634.00 --- 7/1/2011
       
Total Amount: $16,797,634.00 $16,797,634.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
   
1. Design 9/15/2011 9/30/2012    
2. R-O-W & Utility Relocation 9/30/2012 4/30/2013    
3. Construction 6/1/2013 9/30/2014    


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue