Project Detail
Project Main Menu

Project Overview
Project Name: FCM: Haymarket Gainesville Community Library
Project Type: Library
Project Description: The Gainesville Community Library is a 20,000 square feet full service library with regular services such as circulation, information services, readers’ advisory services, children’s programs and services, an online library catalog, electronic resources, web-based library services, self check-out, public Internet access and wireless public Internet access, and an introduction of a cafe. A Bushy Park House, built in last half of 18th century was situated on Bull Run Tract and was owned by Mann Paige II. Threatened by development, the house was relocated from Catharpin Road to the future site of the library. Bushy Park House will be featured as an interpretive center at the new Gainesville Library. The Gainesville Community Library will be located at the intersection of Route 15 and Lightner Road.
Project Manager: Seena Vasan     send an email
Alternate Manager: John W. Mitchell     
Agency Name: Public Works - Facilities Construction Management QPR?: Yes
Magisterial District: Gainesville
Original Budget: $11,657,623.00

Revised Budget:

$13,246,445.00
Original Start Date: 1/1/2006

Revised Start Date:

10/1/2011
Original End Date: 6/30/2008

Revised End Date:

10/15/2015
Last Updated On: 6/20/2016 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. General fund provides $50,000 towards this project and will provide operating funds upon occupancy. Developer contributions (proffers) provide $1,823,405 towards this project. Debt financing approved by voters during the 2006 bond referendum provides $9,940,000 for this project.

$11,657,623.00 $13,246,445.00 7/1/2011
       
Total Amount: $11,657,623.00 $13,246,445.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
   
1. Construction NTP issued to EE Reed 5/21/2014 8/14/2015 9/15/2015    
2. Substantial Completion 9/15/2015 9/15/2015    
3. Furniture, Equipment, and Book installation 9/15/2015 10/15/2015    


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue