Project Detail
Project Main Menu

Project Overview
Project Name: DPR: Fuller Heights Park
Project Type: New Construction
Project Description: Construction of a new park that will provide 4 little league fields, 1 open play field, a playground, basketball courts, restroom/concessions building and parking.
Project Manager: Debra D. Andrew     send an email
Alternate Manager: John Lyons     
Agency Name: Park Authority QPR?: Yes
Magisterial District: Potomac
Original Budget: $5,023,286.00

Revised Budget:

$6,272,242.00
Original Start Date: 7/1/2011

Revised Start Date:

7/1/2011
Original End Date: 9/1/2013

Revised End Date:

5/1/2015
Last Updated On: 5/29/2015 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. Proffers

$0.00 $1,588,574.00 4/22/2014

2. Year End Funds

$0.00 $335,382.00 12/10/2013

3. Stream Mitigation Funds

$523,286.00 --- 6/27/2013

4. General Obligation Bond

$4,500,000.00 $3,825,000.00 7/1/2011
       
Total Amount: $5,023,286.00 $6,272,242.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
Assigned
Staff
 
1. Design and Permitting 7/1/2011 7/1/2012 Phil Puzick  
2. Construction 7/1/2012 3/15/2013 7/1/2013 5/1/2015 Armajit Riat  


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue
Project revised to 3 Little League fields with league building to meet budget constraints

2. Schedule/Timing Issues     

 

Date

Issue
4/18/2015Project Complete, Grand opening held
5/21/2013Project re-bid following minor plan revisions to reduce scope. Bids are due in 5/29/2013

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue