Project Name: DPR: Lake Ridge Trail
Project Type: New Construction
Project Description: Construct Trail from McCoart Building to the Town of Occoquan
Project Manager: Debra D. Andrew     send an email
Alternate Manager:     
Agency Name: Park Authority QPR?: Yes
Magisterial District: Occoquan
Original Budget: $614,269.00

Revised Budget:

$1,054,227.00
Original Start Date: 7/1/2011

Revised Start Date:

7/1/2014
Original End Date: 7/1/2016

Revised End Date:

7/1/2018
Last Updated On: 6/20/2016 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. Proffers

$0.00 $439,958.00 5/10/2016

2. General Fund

$614,269.00 --- 7/1/2011
       
Total Amount: $614,269.00 $1,054,227.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
Assigned
Staff
 
1. Lake Ridge Park to Hedges Run 7/1/2011 7/1/2014 7/1/2012 12/31/2016 Donnie Kozanecki  
2. Bridge from Hedges Run to Mohican 8/1/2012 5/1/2016 8/1/2013 12/1/2017 Donnie Kozanecki  
3. Hedges Run to Mohican 7/1/2014 12/1/2015 8/1/2015 12/1/2017 Donnie Kozanecki  
4. Install 40 foot bridge 7/1/2014 12/1/2016 7/1/2015 12/1/2017 Donnie Kozanecki  
5. Hooes Run Boardwalk 7/1/2015 12/1/2017 7/1/2016 7/1/2018 Donnie Doanecki  
6. 14,000 foot segment to Occoquan 7/1/2015 12/1/2017 7/1/2016 7/1/2018 Donnie Kozanecki  


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue
4/21/2015Project Resumed
12/20/2014Construction of trail on hold pending FY16 budget approval
4/14/2014Agreement with LRPRA approved 4/8/14.

3. Fiscal/Resource Issues     

 

Date

Issue
4/21/2015Project funding confirmed, project resumed

4. Impact on Other Projects     

 

Date

Issue