Project Name: ES: COW BRANCH PHASE I
Project Type: STREAM RESTORATION
Project Description: Restore approximately 1,500 lf of the Cow Branch stream corridor from Route 1 to Mellott Road. Includes a $250,000 match by DCR Grant (2010 WQIF-06) for Cow Branch I and II)
Project Manager: Charles B. Williamson     send an email
Alternate Manager: Thomas E. Dombrowski     
Agency Name: PUBLIC WORKS QPR?: Yes
Magisterial District: Woodbridge
Original Budget: $360,000.00

Revised Budget:

$360,000.00
Original Start Date: 1/1/2010

Revised Start Date:

Original End Date: 6/30/2012

Revised End Date:

6/30/2015
Last Updated On: 1/15/2013 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. Partial funding provided by DCR grant WQIF 2010-P06. 50/50 match in the amount of $250

$0.00 $250,000.00 7/1/2011

2. CIP budget

$360,000.00 $110,000.00 5/31/2010
       
Total Amount: $360,000.00 $360,000.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
Assigned
Staff
 
1. Complete 60% engineering design 1/1/2010 3/31/2010  
2. Obtain regulatory approvals (JPA) 3/31/2010 3/31/2011 TED  
3. DCR WQIF Matching Grant Award 11/1/2010 3/31/2011 CBW  
4. Complete construction of main channel modifications 7/15/2011 5/20/2011 10/31/2011 12/31/2011 CBW  
5. Construct wetland tributary improvements along Melltt Road. 8/1/2011 12/1/2011 12/31/2011 3/31/2012 CBW  
6. Complete vegetative plantings. 10/15/2011 11/15/2011 11/15/2011 12/21/2011 TED  
7. Annual monitoring for success criteria 6/1/2012 6/30/2015 TED  


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue