Project Detail
Project Main Menu

Project Overview
Project Name: FC: Adult Detention Center Expansion and Renovation
Project Type: New Facility Construction
Project Description: The Adult Detention Center Expansion will provide an additional 200 beds for housing inmates and all support functions to operate the addition and existing facility. Renovation of the existing ADC will provide additional staff space and reconfigured inmate space.
Project Manager: Seena Vasan     send an email
Alternate Manager: Matthew P. Corneliussen     
Agency Name: Public Works QPR?: Yes
Magisterial District: Brentsville
Original Budget: $39,366,634.00

Revised Budget:

$79,931,414.00
Original Start Date: 1/1/1992

Revised Start Date:

Original End Date: 6/30/2006

Revised End Date:

9/1/2010
Last Updated On: 7/8/2011 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. General Fund Debt

$39,366,634.00 $79,931,414.00
       
Total Amount: $39,366,634.00 $79,931,414.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
Assigned
Staff
 
1. Hire Architect 1/1/1992 6/1/1992  
2. Facility Program 7/1/1992 9/1/1992  
3. Facility Design 10/1/1992 11/1/1993  
4. Revise Community Based Corrections Plan 3/15/2002 7/5/2002  
5. County Review of CBCP 7/6/2002 7/19/2002  
6. Revise and Complete Construction Documents 8/1/2002 5/1/2003 4/2/2003 6/1/2004  
7. Design Permit Review 4/2/2003 9/30/2004 7/6/2003 4/22/2005  
8. Contract prepration and Bidding 4/5/2003 7/1/2004 9/10/2003 6/22/2005  
9. Drawing revisions (for cost reduction) 9/30/2005 1/17/2006 architect  
10. Re-issue Bid for Expansion 1/9/2006 2/3/2006 Purchasing  
11. Bid period (Expansion) 2/3/2006 3/29/2006 purchasing  
12. Award Contract (Expansion)(BOCS) 10/15/2003 6/20/2005 11/7/2003 5/16/2006 PW  
13. New Construction (200 Bed expansion) 10/10/2003 6/20/2006 6/10/2005 7/10/2008 PW  
14. Staff training and transition 7/1/2008 7/11/2008 9/30/2008 10/10/2008 ADC  
15. Advertise and bid renovation 5/1/2008 12/3/2008 8/30/2008 2/14/2009 PW  
16. Renovate existing ADC building. 6/26/2009 6/30/2009 9/19/2010 PW  


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue
3/15/2011The reimbursement package in an amount of $3.7 mill was submitted on 3/10/2011 for the renovation work. The VaDOC has 60 days to process the request. Staff anticipates recieving the funds within the next 90 days, or by end of the current fiscal year.

4. Impact on Other Projects     

 

Date

Issue