Project Name: ESD: Hylbrook Park Stream Restoration
Project Type: Stream Restoration/Slope Stabilization
Project Description: Restore 1000 linear feet of stream. Provide slope stabilization via reinforced soil lifts along 150 feet of stream. Floodplain study is underway.60% design plans are currently under review by County Staff.
Project Manager: Benjamin A. Eib     send an email
Alternate Manager: Thomas E. Dombrowski     
Agency Name: Public Works QPR?: Yes
Magisterial District: Woodbridge
Original Budget: $585,000.00

Revised Budget:

$998,905.00
Original Start Date: 6/30/2013

Revised Start Date:

Original End Date: 6/30/2014

Revised End Date:

12/15/2016
Last Updated On: 10/3/2016 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. Marumsco Creek CIP

$292,500.00 $633,280.00 7/15/2014

2. SLAF Grant

$292,500.00 $365,625.00
       
Total Amount: $585,000.00 $998,905.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
Assigned
Staff
 
1. Feasibility 12/1/2013 7/15/2014 3/1/2014 9/15/2014 TED  
2. Design 3/1/2014 7/1/2014 7/15/2015 TED  
3. FEMA Floodplain Study and CLOMR FEMA approval 11/15/2014 6/15/2016 6/15/2017 ted  
4. Construction 7/1/2014 10/1/2015 12/31/2014 10/15/2016 TED  
5. Closeout 3/31/2016 9/15/2016 5/1/2016 10/15/2016 TED  


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue