Project Detail
Project Main Menu

Project Overview
Project Name: ESD: Hylbrook Park Stream Restoration
Project Type: Stream Restoration/Slope Stabilization
Project Description: Restore 1000 linear feet of stream. Provide slope stabilization via reinforced soil lifts along 150 feet of stream. Floodplain CLOMR IS SUBMITTED .Design plans are approved and construction is completed. Planting of site will happen in Febuary .
Project Manager: Benjamin A. Eib     send an email
Alternate Manager: Thomas E. Dombrowski     
Agency Name: Public Works QPR?: Yes
Magisterial District: Woodbridge
Original Budget: $585,000.00

Revised Budget:

$998,905.00
Original Start Date: 6/30/2013

Revised Start Date:

Original End Date: 6/30/2014

Revised End Date:

12/15/2016
Last Updated On: 5/16/2017 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. Marumsco Creek CIP

$292,500.00 $633,280.00 7/15/2014

2. SLAF Grant

$292,500.00 $365,625.00
       
Total Amount: $585,000.00 $998,905.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
Assigned
Staff
 
1. Feasibility 12/1/2013 7/15/2014 3/1/2014 9/15/2014 TED  
2. Design 3/1/2014 7/1/2014 7/15/2015 TED  
3. FEMA Floodplain Study and CLOMR FEMA approval 11/15/2014 6/15/2016 6/15/2017 ted  
4. Construction 7/1/2014 10/1/2015 12/31/2014 10/15/2016 TED  
5. Closeout 3/31/2016 9/15/2016 5/1/2016 2/15/2017 TED  


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue