Project Name: ESD: Oak Street Channel Stabilization
Project Type: Stream channel stabilization/infrastructure protection
Project Description: Add a new end wall to the existing culvert so stream flow is redirected and better aligned with existing channel. Stabilize banks, provide protection for existing sanitary sewer, and reduce velocity of culvert outflow.Project is approved by PWC and VDOT. Project is constructed and completed on 815/2015.
Project Manager: Thomas E. Dombrowski     send an email
Alternate Manager: Benjamin A. Eib     
Agency Name: Public Works - Environmental Services QPR?: Yes
Magisterial District: Coles
Original Budget: $225,000.00

Revised Budget:

$275,000.00
Original Start Date: 10/1/2011

Revised Start Date:

Original End Date: 7/1/2013

Revised End Date:

12/1/2015
Last Updated On: 2/19/2016 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. Bull Run Watershed OCA 40026

$225,000.00 $275,000.00 7/1/2012
       
Total Amount: $225,000.00 $275,000.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
Assigned
Staff
 
1. DESIGN IS APPROVED BY PWC 10/1/2011 10/1/2014 5/15/2015 ted  
2. Floodplain Study/CLOMAR, Under FEMA review. 3/1/2014 6/1/2015 6/1/2016 ted  
3. Construction 3/1/2015 6/15/2015 9/1/2015 ted  


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue
8/15/2015Project construction is completed
5/28/2015Water Quality Permit from USCOE has been recieved
5/28/2015Floodplain review by FEMA is almost completed

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue