Project Detail
Project Main Menu

Project Overview
Project Name: ESD: Sudley Place Reforestation and Bioretention
Project Type: Reforestation, SWM/BMP Retrofit
Project Description: Reforestation of 3 acres within HOA common area. New biorention facility within HOA common area.
Project Manager: Julie Flanagan     send an email
Alternate Manager: Benjamin A. Eib     
Agency Name: Public Works - Environmental Services QPR?: Yes
Magisterial District: Gainesville
Original Budget: $133,000.00

Revised Budget:

$72,000.00
Original Start Date: 7/1/2012

Revised Start Date:

Original End Date: 7/1/2013

Revised End Date:

6/30/2014
Last Updated On: 8/13/2014 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. Bull Run Watershed OCA 400026

$133,000.00 $72,000.00 7/1/2012
       
Total Amount: $133,000.00 $72,000.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
   
1. Buffer Reforestation 7/1/2013 9/15/2013 1/3/2014    
2. Record Deed of Easement 7/1/2013 8/31/2013 12/31/2013    
3. Bioretention Construction 7/1/2013 1/7/2014 11/1/2013 2/20/2014    
4. Install Signage 3/18/2014 4/7/2014 5/1/2014    


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue