Project Name: PM: Owens Building Power Redundancy Project
Project Type: Construction/Electrical
Project Description: Install two new 750 KW Generators, UPS Systems, transfer switches and replace electrical panels, to ensure power redundancy for The PWC Public Safety Answering Point (911) and Department of Information Technology’s Data Center
Project Manager: Said G. Said     send an email
Alternate Manager: Matthew P. Corneliussen     
Agency Name: Public works QPR?: Yes
Magisterial District: Occoquan
Original Budget: $1,616,450.00

Revised Budget:

$1,616,450.00
Original Start Date: 3/21/2014

Revised Start Date:

Original End Date: 8/30/2015

Revised End Date:

Last Updated On: 9/28/2015 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. BOCS approved TBA funds from the E-911 Restricted fund to the Owens Building Power Redundancy Project

$1,616,450.00 --- 2/25/2014
       
Total Amount: $1,616,450.00 $1,616,450.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
Assigned
Staff
 
1. Design Services : Moseley Architects completed the design and specifications 4/4/2014 8/30/2015  
2. Site plans submitted to Land Development on 8/6. Plans approved Construction plans submitted to Building Development on 8/11. Comments on first submittal expected on 8/28. 8/11/2014 10/7/2014  
3. Property Management, Purchasing and Moseley are preparing the Project Manual and IFB documents for the County Attorney's review. 9/1/2014 8/11/2014 9/26/2014 Said Said  
4. IFB issued on October 9, 2014. Bids received November 13, 2014. Lowest Responsive bidder Trumbo Electric, Inc. Bid Amounts $1,410,450 10/9/2014 11/13/2014 Purchasing-PW  
5. BOCS approved Award of Construction Contract to Trumbo Electric Inc. 1/6/2015 1/6/2015  
6. Notice To Proceed (NTP)issued on 01/25/2015. Construction period to final completion is 180 days 1/13/2015 1/25/2015 Purchasing-PW  
7. Construction Work started. underground conduit bank installed. Interior conduits and junction boxes installed in the electrical room, janitorial closet, UPS room and above corridor ceiling.. 2/19/2015 5/21/2015 Trumbo Electric  
8. two UPS systems delivered and installed in Place. 4/8/2015 5/21/2015 Contractor  
9. Concrete pad for the Generator is constructed 4/27/2015 5/5/2015 Contractor  
10. The two new generators were delivered and installed at site. 5/29/2015 5/29/2015 Contractor  
11. Disconnected power from Owens Building, Replaced Main Switchboard, wired all electrical panels, and generators, tested the new generators and reconnected electrical power to the building 7/11/2015 7/12/2015 B&G DoIT  
12. New UPS Systems , tested and put in operation. 8/7/2015 8/7/2015 PM, B&G, DoIT  
13. Substantial Completion, walk through and generate punch list items. 8/18/2015 8/18/2015 Engineer , PM &B&G  
14. Training for County Staff performed by the Contractor and the equipment manufacturers 8/24/2015 8/24/2015 Vendors  
15. Project is completed. 8/28/2015 8/28/2015  


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue
8/8/2015Second power outage lasts for one hour. New Uninterruptable Power Supply(UPS) Systems are put in-line.
7/11/2015Power outage of the entire Owens building is scheduled from 6:00 am Saturday 7/11 till 6:00 PM Sunday 7/12. All services will be directed to alternate site at Western District Police Station.

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue